This pre written wall and floor tiling safe work method statement template provides the typical safety controls and possible hazards associated with the installation of floor and wall tiles use of mortar grouting and associated items.
Safe work method statement wall and floor tiling.
Plaster shall be finished rough in order to have a strong key for tiling works.
The wall floor tiling safe work method statement breaks the tilers work activity into logical job steps lists the typical hazards associated with each of these steps and describes the control measures implemented to eliminate or control the risk for the tilers safety.
This method statement defines the activities and the sequences which are to be carried out and to describe in general the methodology to be used in work execution related to ceramic floor tiling works for name of project to ensure compliance with the conditions of contract contract specifications and health safety and environmental requirements consistent with the approved drawings relevant specifications and boq.
Obtain necessary clearances and approvals from engineers including mep clearance.
Method statement for tiling at walls for concrete block walls and concrete walls to be finished with tile apply a leveling coat of plaster minimum 12 mm thick sufficient to cover the unevenness of the substrate and to make walls true vertical.
Obtain necessary clearances and approvals from engineers including mep clearance before putting the tiles on walls.
Selected working area should be barricaded to avoid accidents damages.
Apply the mortar to the back of tile and tap in into place at the required level position to the wall.
Identify and mark the wall file finishes level from the design drawings.
Wall and floor tiling aren t necessarily the first activities which come to mind when thinking about high risks construction activities and safe work method statements but like most construction jobs tiling does involve some concrete hazards which require ongoing and conscious management.
Safe work method statements tiling services workplace health and safety have developed a range of approved safe work method statements for the performance of activities and other tasks associated with the undertaking of tiling at a workplace.
Mix the cement and adhesive cement thoroughly with clean water.
Move the required tiles ordinary portland cement and adhesive cement to the designated work area.
Below is the step wise safe work method of statement for ceramic wall tiles installation.
Selected working area should be barricaded to avoid accidents damages.